Forecast the cost of post-order modifications

Road going into the distance with the word forecast at the start

I found that asking Engineers and Buyers to forecast costs for post-order modifications an excellent cost control tool and procurement skill

This usually started when bid analysis summaries were submitted for subcontractor selection and funding approval. They would recommend placing an order on a vendor or contractor with an original order cost

I would ask the authors of the bid analysis to forecast an outturn cost (using their experience) by estimating the expected growth post-order due to future modifications (POMs allowance)

If agreed I would grant authorisation to place the order/subcontract and use the agreed POMs allowance to manage growth without applying for extra funding

Encouraging the use and ownership of this system was not easy:

  • Buyers tended to be only used to funding approvals for exact amounts ie the original order value and multiple order amendments when occurred
  • Engineers tended to think this was not their area of expertise and should be left to “commercial people”
  • Both sometimes thought that if the original control estimate for the project had say a +10% accuracy than that is what the POMs should be

However this is not the case as the project has moved on and with it the detail. Those involved with analysing the bids should, without a lot of time, be able to use their experience to take a better view at this order placement stage

Typical POMs allowances that I came across (but depends on the complexity and design completeness and contract type) were:

  • Catalogue items 0% (standard multi-supplied items)
  • Equipment packages 4% (eg design reviews introducing bespoke changes)
  • Civil contracts at least 10% (eg impact of unknown ground conditions and weather)
  • M&E contracts not easy to forecast. I have seen them grow by as much as 40%. Heavily depends on the thoroughness of the tendered design

New forecasts (order value plus POMs allowance) can then be fed into the overall project cost forecast. When orders are completed and closed out, they are replaced by actual order amounts, hopefully returning any excess allowance to the project

By David

Retired Capital Projects Manager